Blog

Progress claims that do not restart the argument

An invoice for a finished job asks one question: will you pay this. A progress claim asks a harder one, which is whether the stage you are claiming has actually been reached.

The person reading it is usually looking for a reason to hold it, and a claim that makes that easy will be held.

Claim against the stages in the contract, not the work you did

The contract sets out the stages and what each is worth. A claim that reorganises them into the way the site actually ran gives the reader something to reconcile before they can approve anything.

Use the contract's own stage names and its own amounts. Where you have done work that crosses two stages, claim the stage that is complete and leave the other until it is.

Show the arithmetic from the start of the job

Every claim should carry the running totals, because the reader's real question is not what this claim is worth but where the job now stands.

  1. Contract sum, including every variation approved so far.
  2. Claimed to date, what the previous claims came to.
  3. This claim, the stage or stages now complete.
  4. Retention held, the amount withheld on this claim and in total.
  5. Balance to complete, what is left in the contract after this one.

Those five lines answer most of the questions that otherwise arrive as an email a week later, and a week later is a week you are not being paid.

Variations are the usual reason a claim is short paid

A variation claimed inside a stage, with no approval attached, is the single most common cause of a claim being cut. The assessor cannot approve what they cannot trace, so they approve the stage and drop the variation.

Keep variations as their own numbered lines, each pointing at the written instruction that created it. A builder's variations register covers how to record them when they arrive, which is the only time the detail is available.

Attach the evidence the assessor would ask for

Photographs of the completed stage, dated, do more than any covering letter. So do the delivery dockets for materials on site but not yet installed, where the contract lets you claim them.

Send it as one link rather than six attachments. The assessor opens one page, sees the lines, the totals and the photographs together, and has no reason to come back to you for the rest.

Claim on the day the contract says

Progress claims run on a cycle, and a claim submitted three days late usually waits a full cycle to be assessed. That turns a small administrative slip into a month of cashflow.

Set the claim date as a recurring task with the site manager as its owner, so preparing it is a job in somebody's week rather than something remembered on the day. Being ready early costs nothing and being late costs a month.

Then track what was claimed against what was certified

The number that matters to a builder is not what you claimed, it is the gap between claimed and certified across the whole job. A single short payment looks like a dispute. Four in a row on the same category is a pattern you can take to a meeting.

Keep both figures against each claim and the gap becomes a column rather than a feeling. It also tells you which parts of your own claims are weakest, which is usually the variations.

What to do first

  • Claim in the contract's stage names, at the contract's amounts
  • Put contract sum, claimed to date, this claim, retention and balance on every claim
  • Give every variation its own line and attach the instruction that created it
  • Photograph each completed stage on the day it completes
  • Put the claim date in somebody's week as a repeating task
  • Record what was certified beside what was claimed, and watch the gap

Subscribe to our newsletter

Keep updated with the latest changes.